NextDecade Provides Third Quarter 2026 Business Update
CEO Commentary
“During the third quarter, we maintained strong momentum on Rio Grande LNG Phase 1 as we continued to advance construction and commissioning activities safely, on budget, and ahead of schedule,” said
“We expect first LNG production from Train 1 in the second quarter of 2027, and substantial completion of Train 1 in the third quarter of 2027, which is a quarter ahead of the guaranteed completion schedule under our EPC contract with Bechtel. The projected timing of these milestones reflects the strong dedication and execution of Bechtel, our employees, and contractors as we continue our transition toward operations.”
“LNG market dynamics remain very favorable for the expected commissioning and start-up of Trains 1 through 5 at
“We also continued to advance our growth initiatives during the quarter. We received authorization from the
Significant Recent Developments
Construction and Commissioning
-
Progress on Trains 1 through 5 under the engineering, procurement, and construction (“EPC”) contracts with
Bechtel Energy, Inc. (“Bechtel”) as ofSeptember 2026 consisted of:
|
|
Overall Completion Percentage |
Engineering |
Procurement |
Construction |
Commissioning |
|||||
|
Trains 1 and 2 |
79.7% |
99.5% |
99.6% |
68.8% |
4.9% |
|||||
|
Train 3 |
55.2% |
97.7% |
93.1% |
24.5% |
— |
|||||
|
Train 4 |
22.5% |
82.9% |
39.2% |
2.8% |
— |
|||||
|
Train 5 |
14.0% |
47.4% |
26.8% |
0.5% |
— |
- During the third quarter of 2026, construction of Phase 1 at the Rio Grande LNG Facility continued to progress safely, on budget, and ahead of schedule, with Train 1 electrical, mechanical, and utility commissioning scopes progressing and installation of the Train 2 main cryogenic heat exchanger completed. Dredging activities for the berths, turning basin, and channel deepening were completed. The gas inlet facilities achieved ready for start-up, and the Bay Runner pipeline reached in-service. We continue to expect first gas into the Rio Grande LNG Facility before year-end 2026.
- We expect first LNG production from Train 1 at the Rio Grande LNG Facility in the second quarter of 2027 and substantial completion of Train 1 in the third quarter of 2027, which is a quarter ahead of the guaranteed completion schedule under the EPC contract with Bechtel.
Development
-
In
July 2026 , theFederal Energy Regulatory Commission (“FERC”) issued its schedule of environmental review for Train 6 at the Rio Grande LNG Facility, and the final Environmental Impact Statement is expected inJune 2027 .
-
In
September 2026 , we received permit authorization from theU.S. Army Corps of Engineers (“USACE”) for Train 6, completing a key regulatory authorization required for construction.
-
In
September 2026 ,FERC approved our uprate request for the Rio Grande LNG Facility, increasing the authorized liquefaction capacity of the first five trains at the Rio Grande LNG Facility to 30.15 million tonnes per annum (“MTPA”).
Financial
-
In
July 2026 ,Rio Grande LNG, LLC (“Phase 1 LLC”) completed an offering of$3.5 billion aggregate principal amount of senior secured notes. The net proceeds from the offering were used to repay approximately$3.5 billion of outstanding borrowings under the Phase 1 LLC credit facilities and to pay fees and expenses associated with the transaction. The tranches of senior secured notes issued were:
-
$1.0 billion aggregate principal amount of senior secured notes due 2031, which bear interest at 5.25% and will mature inJune 2031 ,
-
$500 million aggregate principal amount of senior secured notes due 2034, which bear interest at 5.50% and will mature inJanuary 2034 ,
-
$1.25 billion aggregate principal amount of senior secured notes due 2036, which bear interest at 5.75% and will mature inJune 2036 , and
-
$750 million aggregate principal amount of senior secured notes due 2041, which bear interest at 6.15% and will mature inJune 2041 .
-
In conjunction with the Phase 1 LLC senior secured notes offering, the
$1.0 billion term loan entered into byRio Grande LNG Intermediate HoldCo Borrower, LLC inJune 2026 , and the repayment of Phase 1 LLC credit facilities as a result of those transactions, Phase 1 LLC also reduced the notional amount of certain of its interest rate swaps, resulting in settlement receipts totaling approximately$109.2 million inJuly 2026 . These settlement receipts were used to reduce outstanding borrowings under the Phase 1 LLC credit facilities.
-
In
September 2026 , Phase 1 LLC issued$575 million of senior secured notes in a private placement, which bear interest at 6.72% and will amortize over a period of approximately 18.5 years beginning inJune 2029 , with a final maturity inDecember 2047 . Proceeds were used to reduce outstanding borrowings under the Phase 1 LLC credit facilities and to pay fees and expenses associated with the transaction.
-
In
July 2026 , Rio Grande LNG Train 5, LLC issued a third installment of$100 million and inOctober 2026 issued the final installment of$150 million of 6.56% Senior Secured Notes due in 2050, pursuant to the Note Purchase Agreement entered into in conjunction with the positive final investment decision on Train 5 inOctober 2025 for the issuance of$500 million aggregate senior secured notes, which are now fully issued and outstanding.
Rio Grande LNG Facility
We are constructing and developing the Rio Grande LNG Facility which is located in the
Construction commenced on Phase 1 at the Rio Grande LNG Facility in
The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of 30 MTPA, four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, warehouses, and operations control room, maintenance, and administrative buildings.
Progress on Phase 1 as of
Progress on Trains 4 and 5 as of
Dredging activities for the berths, turning basin, and channel deepening were completed. The gas inlet facilities have achieved ready for start-up, the Bay Runner pipeline reached in-service during the third quarter of 2026, and across the site there is ongoing commissioning of systems to support initial hydrocarbon introduction before year-end 2026.
Development of Additional Liquefaction Capacity
We are developing and advancing the permitting process for Trains 6 through 8 at the Rio Grande LNG Facility. These trains are currently wholly-owned by
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility and adjacent to Trains 1 through 5. In
We are developing Trains 7 and 8 on the western end of the Rio Grande LNG Facility site and expect to pre-file with
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Investor Presentation and Webcast
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, cleaner energy. We are focused on delivering secure and affordable energy through the safe and efficient development and operation of natural gas liquefaction capacity at Rio Grande LNG. Through our subsidiaries, we are constructing and developing the Rio Grande LNG natural gas liquefaction and export facility near Brownsville, Texas, with 48 MTPA of potential liquefaction capacity currently under construction or in development and sufficient space at the site for up to 10 liquefaction trains. NextDecade’s common stock is listed on the Nasdaq Stock Market under the symbol “NEXT.” NextDecade is headquartered in Houston, Texas. For more information, please visit www.next-decade.com.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of U.S. federal securities laws. The words “anticipate,” “contemplate,” “estimate,” “expect,” “project,” “plan,” “intend,” “believe,” “may,” “might,” “will,” “would,” “could,” “should,” “can have,” “likely,” “continue,” “design,” “assume,” “budget,” “guidance,” “forecast,” and "target," and other words and terms of similar expressions are intended to identify forward-looking statements, and these statements may relate to the business of NextDecade and its subsidiaries. These statements have been based on assumptions and analysis made by NextDecade in light of current expectations, perceptions of historical trends, current conditions and projections about future events and trends and involve a number of known and unknown risks, which may cause actual results to differ materially from expectations expressed or implied in the forward-looking statements. Although NextDecade believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that the expectations will prove to be correct. NextDecade’s actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in NextDecade’s periodic reports that are filed with and available from the Securities and Exchange Commission. Additionally, any development of additional expansion trains at the Rio Grande LNG Facility remains contingent upon receipt of requisite governmental approvals, execution of definitive commercial and financing agreements, securing all financing commitments, achieving other customary conditions and making a final investment decision to proceed. The forward-looking statements in this press release speak as of the date of this release. NextDecade may from time to time voluntarily update its prior forward-looking statements, however, it disclaims any commitment to do so except as required by securities laws.
View source version on businesswire.com: https://www.businesswire.com/news/home/20261029623151/en/
NextDecade Contacts
Investors
Megan Light
mlight@next-decade.com
832-981-6583
Media
Susan Richardson
srichardson@next-decade.com
832-413-6400
Source: NextDecade Corporation