NextDecade Provides Second Quarter 2026 Business Update
CEO Commentary
“Construction at
“We are focused not only on bringing our first five trains online, but also on progressing our expansion capacity to maximize NextDecade’s impact in bringing much-needed secure, reliable, and affordable LNG to customers around the world.”
“During the second quarter of 2026, we filed a formal application for Train 6 with the
Significant Recent Developments
Construction and Commissioning
-
Progress on Trains 1 through 5 under the engineering, procurement, and construction (“EPC”) contracts with
Bechtel Energy, Inc. (“Bechtel”) as ofJune 2026 consisted of:
|
|
Overall
|
Engineering |
Procurement |
Construction |
Commissioning |
|
|
Trains 1 and 2 |
74.0% |
99.1% |
97.8% |
58.9% |
0.6% |
|
|
Train 3 |
50.4% |
96.5% |
90.2% |
17.4% |
— |
|
|
Train 4 |
15.5% |
69.4% |
25.4% |
1.4% |
— |
|
|
Train 5 |
9.4% |
26.8% |
19.3% |
— |
— |
- We safely energized our main substation with 138kV power in May, and we seconded over 100 operational employees to Bechtel in June as part of preparations for first LNG production. We continue to expect first gas into the Rio Grande LNG Facility in the second half of 2026 and first LNG production from Train 1 in the first half of 2027.
Development
-
In
May 2026 , we filed a formal application with theFederal Energy Regulatory Commission (“FERC”) for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth.
-
In
June 2026 , we filed an application with theDepartment of Energy for LNG export authorizations for Train 6.
-
In
June 2026 , we executed a Reservation Agreement withBaker Hughes for the supply of main refrigeration compressors for Train 6.
-
On
July 29, 2026 ,FERC released the schedule of environmental review for Train 6, stating that the final Environmental Impact Statement will be issued onJune 25, 2027 .
Financial
-
In
April 2026 , Rio Grande LNG Train 5, LLC issued a second installment of$100 million and inJuly 2026 issued a third installment of$100 million of 6.56% Senior Secured Notes due in 2050, pursuant to the Note Purchase Agreement entered into in conjunction with the positive final investment decision on Train 5 inOctober 2025 , for the issuance of$500 million aggregate senior secured notes. As ofJuly 30, 2026 ,$350 million of these notes were issued and outstanding.
-
In
June 2026 ,Rio Grande LNG Intermediate HoldCo Borrower, LLC (“Phase 1 HoldCo Borrower”) entered into a credit agreement for a$1.0 billion term loan which bears interest at 7.05%, payable in cash or in-kind at our election until the first interest payment date afterJune 2029 and in cash thereafter, and matures inJune 2033 . Net proceeds from this term loan were used to reduce outstanding borrowings under theRio Grande LNG, LLC (“Phase 1 LLC”) credit facilities, to pay fees and expenses associated with the transaction, and to pay general and administrative expenses of Phase 1 HoldCo Borrower.
-
In
July 2026 , Phase 1 LLC completed an offering of$3.5 billion aggregate principal amount of senior secured notes. The net proceeds from the offering were used to repay approximately$3.5 billion of outstanding borrowings under the Phase 1 LLC credit facilities and to pay fees and expenses associated with the transaction. The tranches of senior secured notes issued were:
-
$1.0 billion aggregate principal amount of senior secured notes due 2031, which bear interest at 5.25% and will mature inJune 2031 ,
-
$500 million aggregate principal amount of senior secured notes due 2034, which bear interest at 5.50% and will mature inJanuary 2034 ,
-
$1.25 billion aggregate principal amount of senior secured notes due 2036, which bear interest at 5.75% and will mature inJune 2036 , and
-
$750 million aggregate principal amount of senior secured notes due 2041, which bear interest at 6.15% and will mature inJune 2041 .
-
-
In conjunction with the Phase 1 HoldCo Borrower credit agreement and the Phase 1 LLC senior secured notes offering and repayment of credit facility borrowings, Phase 1 LLC also reduced the notional amount of certain of its interest rate swaps, resulting in settlement receipts totaling approximately
$109 million inJuly 2026 . These settlement receipts were used to reduce outstanding borrowings under the Phase 1 LLC Credit facilities.
Rio Grande LNG Facility
We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south
Construction commenced on Phase 1 at the Rio Grande LNG Facility in
The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 million tonnes per annum ("MTPA"), four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, warehouses, and operations control room, maintenance, and administrative buildings.
Progress on Phase 1 as of
Progress on Trains 4 and 5 as of
The main intake substation at the Rio Grande LNG Facility was energized safely in early
Development of Additional Liquefaction Capacity
We are developing and advancing the permitting process for Trains 6 through 8 at the Rio Grande LNG Facility. These trains are currently wholly-owned by
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility and adjacent to Trains 1 through 5. In
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Investor Presentation and Webcast
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, cleaner energy. We are focused on delivering secure and affordable energy through the safe and efficient development and operation of natural gas liquefaction capacity at Rio Grande LNG. Through our subsidiaries, we are constructing and developing the Rio Grande LNG natural gas liquefaction and export facility near Brownsville, Texas, with approximately 48 MTPA of potential liquefaction capacity currently under construction or in development and sufficient space at the site for up to 10 liquefaction trains. NextDecade’s common stock is listed on the Nasdaq Stock Market under the symbol “NEXT.” NextDecade is headquartered in Houston, Texas. For more information, please visit www.next-decade.com.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of U.S. federal securities laws. The words “anticipate,” “contemplate,” “estimate,” “expect,” “project,” “plan,” “intend,” “believe,” “may,” “might,” “will,” “would,” “could,” “should,” “can have,” “likely,” “continue,” “design,” “assume,” “budget,” “guidance,” “forecast,” and "target," and other words and terms of similar expressions are intended to identify forward-looking statements, and these statements may relate to the business of NextDecade and its subsidiaries. These statements have been based on assumptions and analysis made by NextDecade in light of current expectations, perceptions of historical trends, current conditions and projections about future events and trends and involve a number of known and unknown risks, which may cause actual results to differ materially from expectations expressed or implied in the forward-looking statements. Although NextDecade believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that the expectations will prove to be correct. NextDecade’s actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in NextDecade’s periodic reports that are filed with and available from the Securities and Exchange Commission. Additionally, any development of additional expansion trains at the Rio Grande LNG Facility remains contingent upon receipt of requisite governmental approvals, execution of definitive commercial and financing agreements, securing all financing commitments, achieving other customary conditions and making a final investment decision to proceed. The forward-looking statements in this press release speak as of the date of this release. NextDecade may from time to time voluntarily update its prior forward-looking statements, however, it disclaims any commitment to do so except as required by securities laws.
View source version on businesswire.com: https://www.businesswire.com/news/home/20260730544785/en/
NextDecade Contacts
Investors
Megan Light
mlight@next-decade.com
832-981-6583
Media
Susan Richardson
srichardson@next-decade.com
832-413-6400
Source: NextDecade Corporation